Tuesday 17th May
Mesh added over the original garage door lintle so that the render will stick.
More mesh added over a crack in the brickwork
All meshed-up and ready to go.
Close-up of the render being applied
Frame built inside above window and additional insulation installed.
Scratch coar of render complete.
Wednesday 18th May
Hose side wall of the cinema room has now been plastered
likewise the end wall has received two layers of plasterboard with green glue and a layer of plaster.
The above picture is slightly out of sequence, as this shows the trial fit of the radiator wich actually happened a week or two later
Monday 6th June
Top coat of render has been applied